安装要则
- 发布日期:2009-04-24 10:18:49
- 阅读数:8992
安装要则Installs the important regulation
●檀条可选用管钢(60x40X3mm)或C型钢(100X50x20X3mm)或木方(60X40mm),要做防腐处理。
●檀条间距为660mm,由下往上排布。
●主瓦安装时要根据当地风向,逆向安装,搭接一个瓦波,两侧同时进行。
●安装正脊瓦时将**张脊瓦截掉一段后再安装。
● The strip may select the tube steel (60x40x3mm) either the c section (100x50x20x3mm) or the wooden side (60x40mm), must make the antiseptic treatment.
●The strip spacing is 660mm, upward distributes by under.
●The main tile installs when must act according to the local wind direction, the reversion installment, joins a tile wave, two sides also carry on.
●Installs after when the ridge tile falls the first ridge tile truncation a section to install again.
●Slanting ridge tile installment joining place should saw neat,after ,the slanting ridge tile attire finished, then installs the three contacts tile.
●Fixed is the stainless steel component. When fixed, first uses the electric drill dill hole, the aperture to have nail lead screw to be bigger than 2mm.